BLUE VALLEY HIGH SCHOOL
Project Highlights
Year Completed: 2017
Application: Pool
Location: Stillwell, KS
Featured Product ~ Thermaduct
The project included Thermaduct with an R-Value 12. It was provided with a smooth, white Ventureclad membrane on the interior to prevent the chlorine saturated air from reacting with the aluminum facing of the standard product. To eliminate turning vanes, we provided radius heel elbows with splitters that were also covered with Ventureclad. Thermaduct was used in lieu of epoxy coated metal which was nearly impossible to find locally, and very difficult to work with.
Did you know…
The project had a compressed schedule and the contractor only had (2) weeks to install the unit and ductwork. We were able to complete the project on schedule due to good coordination be-tween the contractor, sales staff & fabricator.
PROJECT TEAM
Contractor: BCI Mechanical
Engineer: Malone, Finkle, Eckhardt & Collins, Inc.